Siemens successfully installs third HVDC platform in the North Sea for TenneT

Major milestone for German offshore grid expansion ---- Successive commissioning of first HVDC offshore grid connections planned between second half of 2014 and first half of 2015

Siemens has completed installation of the offshore platform for the direct-current connection HelWin2. Working under contract from the German-Dutch grid operator TenneT, Siemens has thus achieved a decisive milestone of the German grid connection projects. "We have now installed three high-tech platforms for TenneT in the North Sea. The HelWin2 project is now in the homestretch to begin operation in the coming year," says Jan Mrosik, CEO of the Power Transmission and Smart Grid Divisions of Siemens AG. "We have achieved one more major interim milestone, and are step by step accomplishing the German government's offshore expansion goals", says Lex Hartman, member of TenneT's executive board.


The newly installed HelWin2 platform lies 35 km north of the island after which it was named, Heligoland, directly adjacent to the HelWin1 platform Siemens successfully erected earlier in August 2013. Earlier this year in April Siemens already erected the BorWin2 platform off the coast of Borkum.

All told, Siemens builds five North Sea grid connections for TenneT. The first four are to begin commercial operation successively over the second half of 2014 and the first half of 2015, and in sum total provide transmission capacity of over 2.9 gigawatts. The fifth connection recently ordered this year, BorWin3, is to be ready for operation in 2019.

Using the Siemens technology installed on the platforms, the alternating current power generated by the wind turbines is transformed into direct current for efficient transmission to the mainland. At the associated land-based stations, the electricity generated by the connected wind farms is converted back into the alternating current power required for feeding into the transmission grid. Thanks to Siemens' low-loss high-voltage direct current (HVDC) technology, transmission losses are less than four percent. The platforms are designed to operate for decades in the rough North Sea conditions, and are fully automated.

The HelWin2 platform was constructed and installed by Heerema. The marine and land-based cabling were supplied and laid by the cable specialist Prysmian Group.

HVDC solutions and the associated service activities are part of Siemens' Environmental Portfolio. Around 43 percent of the company's revenues are generated by green products and solutions. That makes Siemens one of the world's leading providers of eco-friendly technology.

This press release and related press photos and datasheets on offshore platforms are available along with other information at: www.siemens.com/press/x-win

Featured Product

TRA SNOW AND SUN - SOLAR TILE MOUNT

TRA SNOW AND SUN - SOLAR TILE MOUNT

You haven't installed a tile mount that is easier to install than the Solar Tile Mount manufactured by TRA Snow and Sun. Solar Tile Mount is used on all tile roof profiles: flat, mid, and high. It is made in the USA of aluminum alloy for strength and excellent corrosion resistance. Solar Tile Mount is built to allow more ease in installation with more rise from the tile surface to the rail for better air flow below panels. The adjustable base is longer than most allowing attachment 6" to the left or right to have the bracket in the base of the pan of the tile and still fasten to the rafter. Solar Tile Mount is adjustable for counter batten systems from ¾" to 3". The horizontal rail is directly above base fasteners giving greater uplift resistance than any other system. For superior waterproofing apply TRA Snow and Sun's butyl backed VersaFlash aluminum flashing. No tile flashing is needed on top of the tile for greater labor and material cost savings.