Heightened risk of suppliers failing to meet their Renewables Obligation

Latest forecasts from Cornwall Insight show a potential shortfall in the Renewable Obligation (RO) buy-out fund of approximately half of the £16.94mn mutualisation threshold. Supplier exits to date alone are not expected to trigger the mutualisation process. However, there is a heightened risk that some active suppliers may now be unable to meet their obligation, which could contribute to triggering mutualisation.

Latest forecasts from Cornwall Insight show a potential shortfall in the Renewable Obligation (RO) buy-out fund of approximately half of the £16.94mn mutualisation threshold. Supplier exits to date alone are not expected to trigger the mutualisation process. However, there is a heightened risk that some active suppliers may now be unable to meet their obligation, which could contribute to triggering mutualisation.


Key findings
• Seven suppliers have exited the market with supply volumes in CP18.
• The total estimated impact of these exits currently sits at approximately half the mutualisation trigger.
• Although mutualisation is unlikely to be triggered by these supplier exits, there is a risk of RO mutualisation due to challenging market conditions.

Tim Dixon, Wholesale Team Lead at Cornwall Insight, said:

"Contrary to the two previous compliance periods where the mutualisation trigger was breached, it is not currently expected that the impact of supplier exits in CP18 will surpass this amount. The seven exited suppliers each had relatively small supply volumes in CP18.

"This does not mean there is not a risk of mutualisation, as we could see further suppliers exit the market in the months ahead, or suppliers failing to meet the late payment deadline.

"In fact, should a supplier comparable to Extra Energy, Economy Energy or Spark Energy - all of which exited the market the previous year - exit the market it would likely tip the scale and push the shortfall in the buy-out fund towards the mutualisation trigger.

"Suppliers have had to face challenging market conditions amid the COVID-19 pandemic, and as a result, there is a heightened risk that some suppliers may now be unable to meet their obligations and instead contribute towards triggering mutualisation. If mutualisation does occur the costs will be recovered from suppliers who met their obligations and ultimately be passed on to the consumers' bill.

"With initial compliance deadlines now having passed, any suppliers with remaining obligations will now need to make a payment by the late payment deadline of 31 October. This could prove a particularly fateful day for the energy sector, with both the RO late payment deadline and the end of the furlough scheme set to end."

Featured Product

Introducing RockIt Smart Slide

Introducing RockIt Smart Slide

Introducing RockIt Smart Slide - the ultimate solution for fast and easy installation of the rail-less RockIt racking system on composition shingle roofs. Smart Slide conforms to UL 441 and TAS 100 (A)-95 for wind and wind-driven rain, providing a super-strong watertight seal that is achieved through compression, in most cases without the need for additional sealant. The waterproofing sealant is embedded deep into the granules of the shingle, thanks to the integrated flexible foam layer that provides cushioning. This ensures a secure fit that conforms to any architectural-style shingle. With UltraGrip Technology™, you can rely on a secure installation, as it absorbs the movement created by thermal expansion and contraction. The pre-installed sealing pads are compatible with all composition shingle roofs, making it the ideal choice, even in ambient temperatures as low as 5 degrees.