Report: Transmission Needed to Meet Corporate America's Growing Demand for Renewable Power
Transmission planners are not accounting for up to 51 gigawatts of potential near-term procurement Corporate energy customers can help by participating in planning processes
WASHINGTON, DC - Big companies are increasingly signing deals to buy wind and solar power, and their large and growing demand may exceed the capacity of existing and planned transmission lines - yet transmission planners arent taking this into account as they draw up their future plans. Thats according to a new report released today by the Wind Energy Foundation (WEF).
"This report demonstrates that there is an immediate need for transmission planners to account for the significant renewable energy goals of corporate purchasers," said John Kostyack, executive director, WEF. "As costs continue to decline for new utility-scale wind and solar projects, an ever-increasing number of large corporate buyers are acting to lock in low-cost renewable power purchase agreements."
The WEF report looked at a range of different scenarios, and found that existing and planned transmission facilities may not be sufficient to deliver the amount of renewable energy companies have already committed to buying. For example, using a conservative set of transmission-building assumptions, the report found that planned transmission build-outs would meet only 42 percent of corporate renewable energy demand in a high-procurement scenario, or 78 percent of the demand in a low-procurement scenario.
"GMs ability to access renewable energy is key to our decisions about where to expand new facilities," said Rob Threlkeld, global manager of renewable energy at General Motors. "Its essential that transmission planners take the growing corporate demand for renewables into account in the planning process. Expanding and upgrading transmission is critical in helping GM access low-cost renewable energy and meet our commitments."
Given these findings, the report recommends that corporate buyers and other large institutional customers take the following actions:
• Encourage transmission planners and state Public Service Commissions to increase access to affordable, renewable energy by approving upgrades and expansion to transmission lines.
• Participate in regional and inter-regional transmission planning conversations to ensure future transmission infrastructure meets customer demand for renewable energy.
• Urge the Federal Energy Regulatory Commission to continue to work to improve the interregional planning process, consistent with Order 1000.
"Any company aiming to buy renewable energy should engage in the transmission planning process," said David Gardiner, president of David Gardiner and Associates, which produced the report on behalf of WEF. "Access to the lowest-cost renewable resources depends on transmission, and corporate renewable energy buyers need to communicate their procurement goals to transmission planners."
###
ABOUT THE WIND ENERGY FOUNDATION
The Wind Energy Foundation is a nonprofit organization dedicated to raising public awareness about the importance of wind and other renewable energy sources through communication, research, and education. This report was produced as part of the multi-sector A Renewable America campaign. For more information, visit: www.arenewableamerica.org and www.windenergyfoundation.org.
Featured Product
OMCO Origin® Factory-Direct Trackers
A One-In-Portrait (1P) solution that support a wide range of solar projects (utility scale, distributed generation (DG), & C&I markets). Manufactured and factory preassembled in the USA at one of OMCO Solar's 5 US plants (AZ, IN, AL, OH), OMCO makes all structural components with domestic steel and now can offer a 100% domestic tracker. OMCO Origin® Factory-Direct Trackers include universal module mounts with options for all commercially available modules, labor-saving bearings with 6 adjustable ways to compensate for posts and terrain issues, and foundation solutions for every terrain including OMCO C Piles.