OPDE finishes construction of new 12MWp solar farm in UK

Constructed during February and March 2014, the site is situated at Alresford in Hampshire and will supply electricity equivalent to consumption of 5,000 homes. • The solar farm was connected to the grid on 23 March, and will produce an output of 12GW per hour a year. • The farm helps strengthen OP

OPDE, a multinational group specialising in the development, investment and operation of solar farms, has recently completed a new 12MWp solar farm in Alresford, Hampshire.

Commencing in February 2014, construction took only two months, and first connection to the grid was made on 23 March.
According to OPDE sources, the new farm, featuring 47,616 PV modules, will generate 11,844MWh a year and supply electricity to 5,000 homes in the UK.
The connection of the new 12MWp farm helps OPDE strengthen its presence in UK, where the firm plans to develop farms for a total output of 150MW in the next few years.

Corporate information: OPDE
OPDE Fotovoltaica, along with MECASOLAR and PROINSO, is a company of OPDE Group that specialises in the development, investment and operation of PV solar farms.

Featured Product

MORNINGSTAR - ReadyEdge

MORNINGSTAR - ReadyEdge

The ReadyEdgeTM (RE-1) accessory is an intelligent system controlling and reporting device meant to make monitoring your solar energy system more transparent. Enabling access to LiveViewTM 2.0 and Morningstar Solar ConnectTM, ReadyEdge provides data from all compatible Morningstar devices in your system. It is designed to be paired with the three ReadyBlock options, up to six total, with the possibility to use multiple ReadyShunts and ReadyRelays. The ReadyEdge is compatible with select Morningstar products.